- What does LEED stand for? Leadership in Energy & Environment Design
- Which was the first LEED Platinum rated building in India? CII-Sohrabji Godrej Green Business Centre
- Which website can you get information about green buildings and the Indian Green Building Council? http://www.igbc.in
- Which credit and how many points are awarded to a project with IGBC AP as a principal design team member. Innovation , one point
- Who can become members of IGBC? Any organisation (Arch, consult, Builder, instituiton etc)
- Which member of the team needs to be a IGBC member for the project to claim the discount? Owner
- Name the 4 Green rating systems available in India through IGBC, and which year these were launched? LEED India New construction -2007, LEED India core & shell in 2007, IGBC green Homes-2009 and IGBC Green Factories -2009
- What is the most recommended time for a project register for rating through IGBC?Initial Design Stage
- At which stage should a project select the rating system the project will be following? Feasibility study
- Where can the fees be found for registration / certification for an IGBC rating system? http://www.igbc.in and Particular rating page
- Which area should not be considered in calculation of fees? Parking area
- What is the next stage after the registration form is submitted on IGBC website? CIR
- What does the project team receive after a project is registered with IGBC?Reference guide & Leed India templates
- What is a CIR? Credit Interpretation Ruling
- What steps should you take before filing a CIR?Check the intent, requirement, calculation details in reference Guide.Check the previously logged CIR’s in the CIR page of IGBC website.Submit a CIR
- With registration, how many CIR’s does project receive for free and how much do subsequent CIRS cost? 2 free & beyond this 5000 per CIR
- Where can you find other project CIR’s? http://www.igbc.in
- What is Pre Certification? To market the project, apply for the leed rating proposed with submittals.
- Which rating systems can you apply for Pre certification? Leed India Core & shell & IGBC Green homes
- Can a project be denied credits in pre certification submittal? Yes.
- If a project achieves “Gold” rating in pre certification, can it apply for Platinum in final certification? Yes
- How often should project team update IGBC on status of project after pre certification? Every 6 months
- If a project is achieving 45 credits and missing one pre requisite, can it still apply for certification? No
- What items should be submitted with the application for certification? All building drawings, Filled in Leed india Templates Calculations Fees
- How long does IGBC take to perform preliminary review? 30 working days
- What is a clarification ? Reply of the Project team for the IGBC preliminary report of Pending & Denied credits.
- What are the contents of Preliminary Review report? CAA (Credit Accept Anticipated, Pending & Denied
- Where are the fees available for certification and what are the fees based on?http://www.igbc.in & fees based on Sq.ft.
- Is there a discount for IGBC members? Yes
- How much time is given for project team to respond to Preliminary review? 30 working days
- How many credits / prerequisites does the IGBC verify on site? Up to six credits and/or prerequisites
- Name the 2 stages at which on site inspection takes place? During construction before awarding the certificate On receiving the final review, what are the options for a project team? Accept or appeal
- How long does a project team have to appeal ? 15 working days
- How much does an appeal cost? Rs. 20,000/credit
- Who reviews an Appeal? What documents should be submitted? Other than the first reviewed party all relevant documents related to that credit alone with All drawings & narration (original submittal for the credit)
- What does a “certified” project receive from IGBC? Certificate, Award letter & metal plaque
- What is the difference between CIR and Clarification? CIR- requires details from IGBC Raised by project team answered by IGBC Clarification-Project team reply for the IGBC preliminary reviewOn
- which website can you find the information on certified projects and accredited individuals of IGBC in India? http://www.igbc.in
- How many copies (soft & hard) of documents need to be sent to IGBC?